Walloon authorities order Google data centre work stopped

Published 29 November 2026 · All stories from this day

Walloon authorities ordered Google to stop construction on a three-hectare data centre building in southern Belgium, saying the work lacked proper planning permission. Google said it had paused work at the site in Farciennes pending further guidance from authorities and would comply with Belgian law.

Regional inspectors visited the site on November 26 and informed Google representatives that construction had to stop, Wallonia spokesperson Nicolas Yernaux said. He described the building as illegal construction and a major offence. The site is on a former mining area covering about 50 hectares.

The order follows a dispute over Google’s proposed change to the project’s planning permission. The company sought to replace the originally planned air-cooling system with a system using water drawn from the nearby River Sambre. Regional authorities refused the amendment, citing concerns about water availability amid drought conditions, and Google challenged that decision in court.

Google’s statement that it had paused construction came after Greenpeace Belgium said work had continued despite the permit dispute. The environmental group said drone footage showed activity at the site. In...